Huntingdon Station Reinforcement Project


FortisBC tendered Canadian Utility Construction to complete the installation of a 180 meter long, 36 inch steel gas pipeline bypass at Huntingdon Station in Abbotsford. The scope also includes the installation of 90 meters of 1 inch liquid odorant pipe and two NPS 24 control valves and all corresponding supports, fittings, and flanges.

FortisBC had Canadian Utility Construction complete the 30 inch and 40 inch tie-ins, which required the management of many different workers, subcontractors, and equipment.

The project required coordination with BC Hydro, Spectra Energy, and FortisBC.


 

 